RAAF Base East Sale

Work Package 2 - As part of ongoing maintenance support on behalf of the Department of Defence, RAAF Base East Sale Work Package 2 comprised of 7,500m2 x 400mm thick Rigid Pavement reconstruction, plus an additional 570 lineal metres of heavy-duty grated drains.

AIR5428 Phase 1 - To support the new Pilot Training Systems for the PC-21 Aircraft, the AIR5428 Project included the construction of a new 26,500m2 x 250mm depth Rigid Pavement Apron to provide a flight line shelter for the RAAF Base’s 28 new aircraft.

RAAF Base Darwin

FY17 MCAF Project - As part of an International Joint Venture on behalf of the USA Airforce, the FY17 MCAF Project included the construction of a new 35,000m2 x 400mm depth Rigid Pavement Apron to support the ongoing training and relationship between the Australia and United States Defence Forces.